SO
Published on 04/30/2026 at 02:22 pm EDT
First Quarter 2026 Earnings Conference Call
Non-GAAP Financial Measures
In addition to including earnings per share (EPS) in accordance with generally accepted accounting principles (GAAP), this presentation also includes historical adjusted EPS excluding: (1) accelerated depreciation from repowering, (2) costs associated with the extinguishment of debt at Southern Company, (3) estimated loss on Nicor Gas capital investments, and (4) estimated loss on plants under construction.
Accelerated depreciation from repowering relates to the repowering of certain wind facilities at Southern Power, which impacted EPS for the three months ended March 31, 2026 and 2025. Accelerated depreciation related to the equipment being replaced will continue until the completion dates of the repowering projects, which are projected to occur through the third quarter 2027. At March 31, 2026, the remaining pre-tax accelerated depreciation is projected to total approximately $335 million in 2026 and $100 million in 2027.
The costs associated with the extinguishment of debt at Southern Company impacted EPS for the three months ended March 31, 2026 and resulted from Southern Company's
redemption of certain junior subordinated notes. Further charges may occur; however, the amount and timing of any such charges are uncertain.
Estimated loss on Nicor Gas capital investments represents costs associated with Nicor Gas capital investments disallowed by the Illinois Commerce Commission in November 2025, which impacted EPS for the three months ended March 31, 2026. Further charges may occur; however, the amount and timing of any such charges are uncertain.
Estimated loss on plants under construction includes charges (net of salvage proceeds), associated legal expenses (net of insurance recoveries), and tax impacts related to Mississippi Power's integrated coal gasification combined cycle project in Kemper County, Mississippi (Kemper IGCC). The charges impacted EPS for the three months ended March 31, 2025. Dismantlement of the abandoned gasifier-related assets was completed at the end of 2025. Site restoration activities are substantially complete, and any additional costs are expected to be immaterial.
This presentation also includes projected adjusted EPS for future periods excluding any additional: acquisition and disposition impacts, charges associated with the Kemper IGCC and/or Plant Vogtle Units 3 and 4, charges associated with Nicor Gas disallowances, impairment charges, costs associated with the extinguishment of debt at Southern Company and its non-state regulated subsidiaries, and/or accelerated depreciation from the repowering of wind facilities. Information concerning the aggregate magnitude of the impacts, if any, from these items on EPS is not available at this time. Accordingly, this presentation does not include a quantitative reconciliation of projected adjusted EPS (which is a forward-looking non-GAAP financial measure) because doing so would involve unreasonable efforts.
Southern Company believes presentation of EPS excluding the items described above provides investors with information comparable to guidance. Management also uses such
measures to evaluate Southern Company's performance.
See slide 5 for a reconciliation of historical adjusted EPS to GAAP EPS
3
Delivering Results Through Growth & Execution
Year-over-year earnings growth across all major businesses in first quarter
Weather-normal sales growth across all customer segments; data centers up 42% vs. Q1 2025
23GW of projects either contracted or in late stages - 6GW projected to finalize in near term
All-Source RFP filed in Georgia for resources by 2033 - process expected to progress through 2027
$26.5B of new DOE loans support the construction of these resources and other infrastructure
Remaining $1.8B projected need includes equity to support base capital plan + 400MW of SPC uprates
4
Q1 2026 Earnings Results
Q1
2026 2025
Earnings Per Share As Reported $1.21 $1.21
Less:
Accelerated Depreciation from Repowering1
($0.10)
($0.02)
Loss on Extinguishment of Debt2
($0.01)
-
Estimated Loss on Nicor Gas Capital Investments3
-
-
Estimated Loss on Plants Under Construction4
-
-
Earnings Per Share Excluding Items
$1.32
$1.23
1 Represents accelerated depreciation related to the repowering of certain wind facilities at Southern Power.
2 Represents costs associated with the extinguishment of debt at Southern Company.
3 Represents costs in 2026 associated with Nicor Gas capital investments disallowed by the Illinois Commerce Commission.
4 Represents charges (net of salvage proceeds), associated legal expenses (net of insurance recoveries), and tax impacts in 2025 resulting from the abandonment and closure activities associated with the Kemper IGCC. 5
Q1 2026 Year-Over-Year Adjusted Driven*
31.23
State-Regukted
Elecarka
Southern Company
Southern
Power
Shares
Q1 2026 Key Drivers
+ Strong Cuomer Usage and G¥owth
+ Investment in stato-regulated utilities
+ Wholesale avenues
- Weather (vs. normal: -34 Q12026 vs. +24 Q12025)
- Higher inQrest expenu
§12025 §12026
Exzltzdes accelerated depreciation related to the repowerir of certain wind farilit at Southern Power, case associated wñti the eztin$uishmem of debt at Southern Company, and costs associated with Nicor Gas capital iwestment disall
Q1 2026 & Projected Full Year Adjusted EPS
Q1 YTD 2026 Adjusted EPS 2026 Projected Full Year Adjusted EPS Guidance1,2
$0.36
$0.12
All Other
($0.90)
LDCs
$0.53
Competitive power,
FERC-regulated pipelines, and other assets under longterm contract
Parent
Electrics
$4.44
$4.60
to
$4.50
$0.10
$0.14
All Other
($0.21)
Parent
LDCs
$0.30
Competitive power,
FERC-regulated pipelines, and other assets under longterm contract
Electrics
$0.99
$1.32
State-Regulated
Utilities
State-Regulated
Utilities
Q2 2026 Estimate = $1.001
1 Excludes any further charges (credits) associated with Plant Vogtle Units 3 and 4, charges (net of salvage proceeds), associated legal expenses (net of insurance proceeds), and tax impacts from the abandonment and closure activities associated with the Kemper IGCC, future acquisition and disposition impacts, future impairment charges, further charges associated with Nicor Gas disallowances, additional costs associated with the extinguishment of debt at Southern Company and its non-state regulated subsidiaries, and/or
accelerated depreciation from the repowering of wind facilities. 7
2 Guidance provided as of February 19, 2026.
Q1 Retail Electricity Sales Growth vs. Prior Year
2.3% total weather-normal sales growth in Q1
Residential sales bolstered by strong customer growth
with addition of 46K new customers since March 2025
Commercial sales increase driven by data center growth of 42% - primarily ramping large loads
Industrial sales led by primary metals (+8%) and
pipeline (+6%) segments
Strong Southeast economy is driven by a diverse mix of
industries, strong employment growth, and in-migration
28 companies announced plans to locate/expanded in Q1,
adding ~4K new permanent jobs and $7B of investment
Rate stability in Alabama and Georgia bolstered by
accelerating sales growth
Weather-Normal Electricity Sales - Class
Q1 2026 vs. Q1 2025
4.6%
Weather-Normal Electricity Sales - Company
Q1 2026 vs. Q1 2025
0.9%
1.5%
2.3%
2.4% 2.5%
2.3%
Residential Commercial Industrial Total Retail
-0.7%
8
Alabama Georgia Mississippi Total Retail
8
Extraordinarily Positioned to Capture Growth
Our Approach To Delivering Value For Customers and Investors
Market Structure
Vertically integrated
Balance Sheet
Size & durability
Business Profile
Utilities & competitive power
Regulation
Constructive & orderly
Scale
To deliver
Location
Growing economies
Large Loads
Benefiting all stakeholders
New Generation
Approved & being built
Experience
To execute
9
~2GW of Additional Large Load Contracted in Q1
23GW of projects have either contracted or are in late stages
increase of ~2GW vs. prior quarter
Combined Large Load Outlook
Projects Ultimate
Ramp
across eight projects in Alabama and Georgia
demonstrating continued momentum and execution
provides robust opportunity for continued progress
100+
10
Prospective Pipeline
Late-stage
75GW+
+5GW
6GW
+5GW
Pipeline Stages
Definition
Prospective Pipeline
Potential large load customers in early to mid-stages that have requested
service in one of our electric service territories
Late Stage
Project is progressing through the review process and likely to execute contract within 12 months
Finalizing
Project is highly likely to execute contract in the near term
Contracted
Fully signed (without material contingencies) and/or regulator reviewed agreement to take electric service
8 Finalizing
6GW
+2GW
Progress
See slide 18 for quarterly comparison of large load outlook by stage
"Committed" projects in Georgia with signed Requests for Service agreements are included within the Late Stage and Finalizing phases
28 Contracted
11GW
since Q4 Call
10
v
New Infrastructure to Reliably Serve Growth
10GW of state-regulated company-owned new resources under construction, with assets projected to be placed in-service each year
Completed
Thermal
Yates Unit 8 (CT)
441 MW
Yates Units 9-10 (CT)
882 MW
Bowen Unit 7 (CC)
780 MW
Wansley Unit 10 (CC)
777 MW
Bowen Unit 8 (CC)
780 MW
Wansley Unit 11 (CC)
777 MW
McIntosh Unit 12 (CC)
797 MW
Storage
Solar
2 BESS Facilities 178 MW1
3 BESS Facilities 587 MW
3 BESS Facilities
610 MW
5 BESS Facilities
1,570 MW
2 Solar + BESS Sites
350MW
2 BESS Facilities
750 MW
2 BESS Facilities
443 MW
500+ Miles of New Transmission Lines
Transmission 11
1) Through April 2026, two BESS facilities, representing 178 MW, have been completed and placed in-service
$26.5B of U.S. Department of Energy Loans
Helps support infrastructure investment, including 10GW of new generation
Low-cost financing is projected to provide an estimated $7B in savings for customers over next 30 years
$26.5B of combined loans at Alabama Power ($4.1B) and Georgia Power ($22.4B) is expected to help satisfy a majority of their capital market needs over next several years
Terms for eligible draws:
Draws through: September 2033
Pricing: Fixed rate, Treasury +37.5bps
Maturity: December 2055
Identified Qualifying Projects by Type
Distribution
20%
21%
36%
Thermal Generation
Transmission
4% 9%
Hydro
10%
Nuclear
Modernization
BESS
Uprates 12
Announced Uprates to Gas Fleet
Millers Branch solar facility Phase I (200MW) placed
into service February 2026
Phases II (180MW) and III (132MW) projected in-service in Q2 and Q4 2026
Repowering of 5 wind facilities (1GW total) underway across Oklahoma and Texas
Projected in-service in 2026-2027
Renewable Projects Underway
400MW of gas uprates announced at four units
across plants Franklin (AL) and Wansley (GA)
Projected combined investment of ~$700M
Construction scheduled to begin in 2026
Commercial operations
projected 2029-2031
Additional 300MW of gas capacity uprate still being pursued
Plant Wansley
100MW
Plant Franklin 300 MW
13
13
Southern Power Projects Update
Proactively Addressing Projected Equity Need Through 2030
$0.5B
$2.3B
$2B Original Equity Need
For Base Capital Plan as shared on Q4 call
Additionalequity for
+$0.3B Southern Power
uprates
Remain on trajectory toward
~17% FFO to Debt by 2029
Assuming ~40% equity for incremental capital investments opportunities
Well-positioned to meet potential incremental growth in a credit supportive and shareholder-focused fashion
ATM
priced in Q1 2026 with forward contracts that settle by 2028
$1.8B
Equity needed to support credit
objective in outlook
Remaining equity to be addressed through 2030
14
25 Consecutive Years of Dividend Increases
Dividends equal to or greater than previous year for 79 years
Southern Company has a long-standing history of providing a regular, predictable and sustainable return to shareholders supported by our dividend
+8¢
+8¢
On April 20, 2026, the Southern Company Board approved an 8-cent dividend increase to an annualized rate of $3.04 per share.1
+7¢
+7¢
+7¢
+7¢
+7¢
+8¢
+8¢
+8¢
+8¢
+8¢
+8¢
+8¢
+8¢
+3¢ +3¢ +3¢
+6¢
+6¢
+6¢
+7¢
+7¢
+7¢
+7¢
History of dividend increases
1Future dividends are subject to approval of the Southern Company Board of Directors and depend on earnings, financial condition and other factors.
20261
15
Southern Company Value Proposition:
Objective of Regular, Predictable and Sustainable
Strategy: Maximize long-term value to shareholders through a customer-, community-, and relationship-focused business model that produces premium, sustainable levels of return for investors
Objective of maintaining a high degree of financial integrity and strong investment-grade credit ratings
Targeting credit profiles that support
'A' ratings for each state-regulated utility and
strong 'BBB+' at Parent
Objective of providing superior risk-adjusted total shareholder return to our investors
79 years
of dividends1
Customer
equal to or greater than the previous year, and
25 consecutive years of dividend increases1
95% of projected capex in
state-regulated
utilities
Supports projected state-regulated electric & gas utility rate base growth of 9%
State-regulated gas $9B
Other
$81B
(2026-2030)
State-regulated electric $68B
8% to 9% projected adjusted EPS growth through 2028
Long-term projected adjusted EPS growth of 7% to 8%2
>90% of Earnings
from state-regulated electric & gas utilities
Projected electric sales growth
of ~10% from 2026 to 2030
Driven by strong economic development that benefits all customers
1 Future dividends are subject to approval of the Southern Company Board of Directors and depend on earnings, financial condition and other factors. 16
2 From 2028 adjusted EPS guidance range of $5.25 to $5.45
Appendix
17
As of Q1 2026
As of Q4 2025
Large Load Stages
75GW+ (125+ projects)
75GW+ (100+ projects)
Prospective Pipeline
Late Stage
Finalizing
Contracted
Recently Contracted Hyperscaler A - 0.5GW Hyperscaler B - 1.4GW
18
Progress Across Large Load Stages vs. Q4 Call
Disciplined Approach to Contracting Large Loads
Provides benefits to customers and adds certainty to our outlook
Contracting Framework
Announced Load Ramps
At least 15 years for data centers and 10 years for all others
Negotiated with minimum bills to cover at least 100%
of annual incremental costs to serve
Tied to the remaining incremental costs to serve over the life of the contract
Tied to termination payment and
based on customer's creditworthiness
Nearly all (~11GW) contracted projects
have begun construction
11GW
6GW
6GW
23GW
2GW
3GW
16GW
10GW
8GW
11GW
2028 2030 Mid-2030s
(as of) (as of) (as of)
Late-Stage
Finalizing
Contracted
19
Georgia Power Storm and Fuel Case Timelines - 2026
Fuel Case (Docket No. 56765)
Storm Case (Docket No. 44280)
February 17 - File application and testimony
February 17 - File application and testimony
April 9 - Staff/Intervenors file testimony
April 17 - Staff/Intervenors file testimony
April 23 - Company files rebuttal testimony
April 30 - Company files rebuttal testimony
May 5-6 - Hearings
May 13-14 - Hearings
May 14 - Briefs and/or proposed orders
May 20 - Briefs and/or proposed orders
May 28 - Energy Committee
May 28 - Energy Committee
May 28 - Final Decision at Administrative Session
May 28 - Final Decision at Administrative Session
June 1 - Rates Adjusted
June 1 - Rates Adjusted
20
Disclaimer
Southern Company published this content on April 30, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on April 30, 2026 at 18:21 UTC.