I N V E S T O R P R E S E N T A T I O N • M a y 2 0 2 6
2021 THAYER LINDSLEY AWARD (BEST GLOBAL DISCOVERY)
Rapid near-term growth to Tier 1 Mid-Tier Producer towards 500 koz AuEq pa at industry leading low costs
Stage 3 Expansion to 300 koz AuEq pa (1.2 mtpa plant commissioning complete and first saleable production recorded early Oct/2025) average AISC of $920/oz AuEq.
Stage 4 Expansion to +400 koz AuEq pa (commissioning targeting late-2027)
Experienced team with proven track-record in Papua
New Guinea
Strong balance sheet and mine cash flow supports mine transformation
Large, high-grade resource with significant growth potential from multiple deposits
$31-35m exploration budget in 2026, potential to increase to $40m upon delivery of
Stage 3 Expansion
Arakompa Maiden Mineral Resource targeting H1 2026.
Significant re-rating potential ahead and during execution
of near-term expansions
Consensus P/NAV of 0.7x NAV vs Mid-Tier Producers at 1.0x NAV(1)
ESG focused with strong relationships with government, community and workforce
Mid-Tier Producer Growth Profile (koz AuEq) K92 Resource Growth Profile (moz AuEq)
0.4
1.6 2.3
3.7
2.7
14.6
4.5
14.6
2.7
1.1 2.2 2.2 2.7
Exceeded
Guidance
Exceeded Guidance
Stage 2
Commissioned In 3Q20
Exceeded
Updated Guidance
Achieved Guidance
Exceeded
Updated Guidance
Exceeded
Guidance
Achieved
Guidance
YE 2017 YE 2018 2Q 2020 1Q 2022 3Q 2022 4Q 2023
2 Drill Rigs in 2018 5 Drill Rigs in 2019 Up to 11 Drill Rigs in 2021-2025, 14 Drill Rigs 2026+
3
Note 1: Data based on analyst consensus estimates provided by BMO Capital Markets. Prices as of April 27, 2026.
Note2 : Kora and Judd resource estimates - refer to technical report dated March 21, 2025, and titled, "Independent Technical Report, Kainantu Gold Mine, Updated Definitive Feasibility Study, Kainantu Project, Papua New Guinea". Blue Lake resource estimate - refer to Technical Report dated March 21, 2025 and titled, "Independent Technical Report, Mineral Resource Estimate Blue Lake Porphyry, Kainantu Project, Papua New Guinea".
K92 Mining - A Unique Tier-1 Opportunity
TSX: KNT
OTCQX: KNTNF
P / NAV 2025 - 2028E Production Growth (koz AuEq)
900
800
+130%
700
Peer Average: 1.0x
600
+41%
500
400
300
200
100
-
Alamos Lundin
Gold
Torex Centerra Fortuna Orla Dundee Wesdome K92 G Mining
4
Note: Prices as of April 27, 2026. 2025 production based on actual results, excluding Centerra. 2028E peer production estimates based on BMO CM Equity Research Model & analyst consensus estimates; K92 2028E production based off projected Stage 4 expansion production rate. NAV based on analyst consensus estimates. Courtesy of BMO Capital Markets.
Attractive Valuation - Compelling Re-Rate Opportunity
TSX: KNT
OTCQX: KNTNF
Operation 1
Company
Reserve Grade
(Au g/t)
2025 Grade
(Au g/t)
BMO Forecasted 2026 AISC
($/oz Au)5
Macassa
Agnico Eagle
8.8
17.4
$1,347
Turquoise Ridge4
Barrick / Newmont
10.6
12.5
$1,591
Island Gold
Alamos Gold
10.6
11.4
$1,421
Mponeng
Harmony Gold
9.4
10.8
$2,180
Kainantu2
K92 Mining
8.5
10.3
$1,300
Segovia
Aris Mining
10.7
9.8
$2,188
Fruta Del Norte
Lundin Gold
7.1
9.5
$1,206
Cerro Negro
Newmont
10.6
8.3
$2,161
Moab Khotsong3
Harmony Gold
9.4
7.9
$2,416
Carlin
Barrick / Newmont
8.2
7.3
$2,027
Pogo
Northern Star
7.2
6.8
$1,666
Obuasi4
Anglogold Ashanti
10.9
6.2
$2,018
Judd 1365 Level
Proven and Probable Reserves (>1 Moz Contained Ounces) and AISC (US$/oz Au)
Note 1: List of operations Reserve Grade and 2025 Grade are based on publicly disclosed 2025 Reserves and may not be exhaustive or up to date.
Note 2: Gold Equivalent 2P Reserves and 2025 Grade - refer to technical report dated March 21 2025 and titled, "Independent Technical Report, Kainantu Gold Mine, Updated Definitive Feasibility Study, Kainantu Project, Papua New Guinea". Kainantu AISC based on company guidance. Note 3: 2026 forecasted AISC for Moab Khotsong shown on a co-product basis.
Note 4: Combined Open Pit and Underground forecast AISC. 5
Note 5: BMO Estimates provided as at April 6, 2026. K92 Estimate is mid-point of 2026 guidance.
Amongst The Highest Grade, Lowest Cost Operating Mines Globally
TSX: KNT
OTCQX: KNTNF
Natural Resource Friendly Jurisdiction
Multiple Senior Mining Companies Operating (Barrick, Harmony, Newmont)
Vibrant democracy since independence in 1975
~89% of exports from mining, oil and gas(1)
Located along Prolific Pacific Ring of Fire, hosting multiple world-class
deposits in both PNG and West Papua
Note 1: 2023 EITI Report.
Large ~830 km2 land package along major regional structure hosting multiple large world-class deposits/mines (Ramu, Wafi-Golpu, Hidden Valley)
Excellent and Well-Developed Infrastructure
Plant, tailings dam and infrastructure located ~6.5 km from mine
portal in Markham Valley (lowlands, plenty of land for construction)
Sealed road from Port of Lae
Hydro grid power (full standby diesel gen sets)
Commercial airstrip 6
Located Amongst World Class Geology and Excellent Infrastructure
TSX: KNT
OTCQX: KNTNF
Fully Funded to Execute Growth Trajectory
Key Financial Data (for the period ending March 31/26)
Symbol
TSX: KNT, OTCQX: KNTNF
Fully Diluted Shares Outstanding
247.1
Cash and Cash Equivalents
US$287m
Debt
US$45m
Remaining Additional Liquidity
Up to US$60m
Strong Cash Balance
Significant Available Liquidity From Credit Facilities
Record Production and Record Gold Prices = Strong Operational Cash Flow Downside Protected During Construction
Shareholder Overview
Analyst Coverage
Puts Purchased for US$5.9m in November 2025 covering 10,000 oz Au per month at $3,500/oz for 12 months (starting Jan/2026), to protect against commodity price risk during the construction. This is not a hedge, this isinsurance, and we retain FULL EXPOSURE TO THE UPSIDE IN COMMODITY PRICES.
Retail / Non-
Filing Institutional 42%
Institutional
53%
Insider (1)
5%
Michael Gray
Andrew Mikitchook
Peter Bell
Varun Arora
Nic Dion
Bryce Adams
Alex Terentiew
Craig Stanley
Harrison Reynolds
Ovais Habib
Ralph Profiti
Wayne Lam
Analyst Transition
Note 1: Insider data includes dilutables. Shareholder information based on data from Irwin.
Chart courtesy of StockCharts.com
7
Corporate Structure
TSX: KNT
OTCQX: KNTNF
Communities
Outstanding Community Humanitarian Initiative awarded by the PNG Chamber of Resources and Energy in 2024 for the K92 Sustainable Livelihoods Agriculture Program
Creating business opportunities for landowner groups via Joint Ventures with local businesses, including $28M spent in 2024
400+ community graduates from K92's Adult Literacy Program in 2024
People
Currently employ +2,300 people (employees plus contractors) with ~92% of total workforce from PNG, including nearly one-third from local communities
Developing skills through multiple MOUs with PNG tertiary institutions
Providing tertiary education scholarships for PNG students with 66 awarded in 2024
Kainantu Endowment established in 2023 to provide tertiary scholarships for students in PNG
Environment
Operate a low-footprint underground mine with downstream tailings impoundment and no permanent surface waste rock facilities
No cyanide used for processing
Target a 25% reduction in GHG emissions by 2030 (against a business-as-usual forecast)
Hydropower is a significant power source at the Kainantu Gold Mine, with solar power
now being investigated
Government
$62.6M in taxes and royalties paid in 2024 (second highest mining corporate income taxpayer in PNG)
$6.6M allocated for Company's inaugural project under the Infrastructure Tax Credit Scheme ("ITCS") of the Government of PNG
Future ITCS projects currently being planned with focus on education, health, infrastructure, and law & order projects
K92 maintains a strong commitment to the prosperity and development of PNG and our host communities through responsible
mining practices and a strategic commitment to delivering sustainable value.
8
Delivering Sustainable Value - 2024 Sustainability Report
TSX: KNT
OTCQX: KNTNF
May 2017
October / December 2021
September 2023
(Long Sections, Looking West)
Kora North Kora and Judd Kora and Judd
1.7 moz at 11.6 g/t AuEq Inferred1
2.3 moz at 9.3 g/t AuEq Measured & Indicated
2.6 moz at 9.1 g/t AuEq Inferred2
2.6 moz at 10.0 g/t AuEq Measured & Indicated
4.5 moz at 8.5 g/t AuEq Inferred3
9
Inferred Resource Grade: 11.6 g/t AuEq (7.1 g/t Au, 34 g/t Ag, 2.2% Cu).
Measured and Indicated Resource Grade: 9.3 g/t AuEq (7.7 g/t Au, 18 g/t Ag, 0.9% Cu). Inferred Resource Grade: 9.1 g/t AuEq (6.8 g/t Au, 26 g/t Ag, 1.3% Cu).
Measured and Indicated Resource Grade: 10.0 g/t AuEq (7.8 g/t Au, 21 g/t Ag, 1.2% Cu). Inferred Resource Grade: 8.5 g/t AuEq (5.7 g/t Au, 27 g/t Ag, 1.5% Cu).
Value Creation Through Discovery
TSX: KNT
OTCQX: KNTNF
2025 Was A Transformational Year for K92
TSX: KNT OTCQX: KNTNF
10
Key Figures
Amount
2026 Production
190,000 to 225,000 oz AuEq
2026 By-product Cash Cost
US$710 to US$770/oz Au
2026 By-product AISC
US$1,250 to US$1,350/oz Au
2026 Co-product Cash Cost
US$980 to US$1,040/oz AuEq
2026 Co-product AISC
US$1,480 to US$1,580/oz AuEq
2026 Exploration
US$31 to US$35 million
2026 Growth Capital
Stage 3 Expansion Capital
Stage 4 Expansion Capital
US$100 to US$108 million US$25 to US$28 million US$75 to US$80 million
Note: Gold equivalent production based on the following commodity prices: Gold $3,400/oz; Copper $4.40/lb, and; Silver $32.50/oz.
Key Highlights
Production Growth: Production in H2 2026 is expected to be the strongest, driven by the ramp-up of ore tonnes mined and processed from two new mining fronts & the completion of major expansion enabler projects in 1H 2026
Record Exploration Program: Total rigs to increase to 14 in Q1 2026 from 12 rigs currently - focused on highly prospective near-mine and regional targets
Growth Capital: As at March 31, 2026, 96% of the Stage 3 Expansion growth capital is either spent or committed, and the project remains on budget. Given the strong financial position with record net cash achieved at YE 2025, Stage 3 Expansion capital expenditure nearing completion, already mobilized contractors and a proven Project Owner's Team, K92 is bringing forward several growth and Stage 4 Expansion projects in 2026, including the following key items:
Stage 4 Expansion Power Plant Upgrade to 15.3 MW ($6 million)
Stage 4 Expansion Haul Road Upgrade ($5 million)
132 kV Power Supply and Line Upgrade ($9 million) - Increase reliability and delivery capacity of clean hydro electricity for the Stage 4 Expansion. Key part of our 2030 GHG Reduction Target strategy. Long-term recovery of capital from reduced operating cost expected.
Stage 4 Expansion Water Treatment and Management Upgrade ($8 million)
Stage 4 Expansion Engineering, Project Management & Owners' Team ($10
million)
Camp Expansion and Facilities Upgrade ($5 million)
Stage 4 Expansion Vertical Mine Development ($11 million)
Port Upgrade ($3 million) - Improve efficiency and capabilities in handling larger volumes of concentrate for the Stage 4 Expansion at the Port of Lae.
Kainantu Community Affairs Office ($3 million)
11
2026 Operational Guidance - Another Major Step Forward Planned
TSX: KNT
OTCQX: KNTNF
Plant Commissioning
Completed Dec 2025
Stage 3
New Stage 3 Process Plant Operating with Stage 2A Plant on Care and Maintenance
Targeting Late 2027 Commissioning
4Q 2020 2Q 2023
Stage 2
Low Capex Upgrades to
Stage 1 Process Plant
Low Capex Upgrades to
Stage 2 Process Plant
Stage 4
Via Low Capex Expansion of Stage 3 Plant (Upgrade Flotation & Filter Press). Stage 2A Plant Available for Next Stage of Expansion.
Note: Numbers presented are rounded figures and correspond with the level of significant figures presented in press release and in the presentation. 12
Systematically Executing to Become a Tier 1 Mid-Tier Producer
TSX: KNT
OTCQX: KNTNF
AuEq Production (koz), Cash Cost ($/oz AuEq) and AISC ($/oz AuEq)
Significant Portion of Sustaining Capex is for Upcoming Expansions
Stage 2 Expansion
Plant Commissioned
Operational Impact Due to Temporary Suspension of Underground Mining
Operational Performance - Since Commercial Production
TSX: KNT
OTCQX: KNTNF
1Q19
2Q19
3Q19
4Q19
1Q20
2Q20
3Q20
4Q20
1Q21
Throughput optimally reduced to maximize recoveries at higher feed grade
2Q21
3Q21
4Q21
1Q22
2Q22
3Q22
4Q22
1Q23
2Q23
3Q23
4Q23
1Q24
27kt
38kt 32kt 30kt
47kt 49kt
65kt
69kt
73kt 76kt
88kt
100kt
100kt
109kt
118kt 122kt
118kt
112kt
121kt
131kt
152kt
2Q24
3Q24
4Q24
1Q25
2Q25
3Q25
4Q25
1Q26
96kt
105kt
97kt
103kt
130kt
137kt
142kt
186kt
1Q19
2Q19
3Q19
4Q19
1Q20
2Q20
3Q20
4Q20
494m
691m
740m
Kainantu Mine Execution
1,220m
1,174m
1,560m
1,683m
1,902m
Operational Impact Due to Temporary Suspension of Underground Mining
1Q21
2Q21
3Q21
4Q21
1Q22
2Q22
3Q22
4Q22
1Q23
1,045m
1,544m
1,583m
1,528m
1,540m
1,826m
1,887m
2,221m
2,278m
2Q23
3Q23
4Q23
1Q24
1,682m
2,173m
2,227m
2,649m
2Q24
3Q24
4Q24
1,938m
2,190m
2,571m
1Q25
2Q25
3Q25
4Q25
1Q26
2,494m
2,466m
2,477m
2,787m
3,007m
1Q19
2Q19
3Q19
29kt 38kt 67kt
36kt 68kt 104kt 30kt 85kt 115kt
4Q19
1Q20
40kt
55kt
83kt
82kt
123kt
136kt
2Q20 38kt 77kt 115kt
3Q20
4Q20
74kt 71kt
92kt
137kt
166kt
208kt
1Q21
2Q21
3Q21
4Q21
1Q22
51kt
72kt 89kt 108kt 100kt
140kt 105kt
114kt
117kt 109kt
191kt 177kt
203kt
Ore Mined
225kt 209kt
2Q22
3Q22
4Q22
1Q23
2Q23
3Q23
4Q23
114kt 122kt 111kt 118kt 109kt 124kt
155kt
113kt
148kt 176kt 160kt
157kt
181kt
228kt
192kt
270kt
287kt 278kt
267kt
306kt
Waste
348kt
1Q24
2Q24
3Q24
4Q24
1Q25
111kt 99kt 112kt 97kt 104kt
127kt 147kt
178kt 209kt 211kt
238kt 246kt
290kt
306kt
315kt
2Q25
3Q25
4Q25
133kt 152kt 158kt
206kt
201kt
246kt
339kt
354kt
404kt
TSX: KNT
OTCQX: KNTNF
14
1Q26
154kt
224kt
378kt
Total Ore Processed (kt) Total Development (m) Total Mined Material (kt)
Strong Process Plant Performance
Recoveries
Gold Copper
TSX: KNT OTCQX: KNTNF
1
Twin Incline
Kora-Irumafimpa Planned Twin Incline and Development Long Section (Looking West)
3
2
2
4
2
2
1
5
Scope: High Speed 2.9km twin incline, capable of +5 mtpa with conveyors
Status: Effectively Complete
Impact: Transforms material handling efficiency with large and high-speed travel way.
2
Ore Pass System
Scope: Raise Bore Ore and Waste Pass System to connect Main Mine with Twin Incline
Status: First pass operational, second pass scheduled for completion in late-Q2, third pass development commencing mid-year.
Impact: Transforms material handling efficiency, improves mining cycle at the Main Mine. Vast majority material to travel via the highly efficient twin incline.
3
Puma Vent Incline
Scope: Twinning of the existing puma incline for vent Status: Breakthrough completed late-February Impact: +150m3/s (+75% vent flow increase) recorded from breakthrough of Puma and Internal Ramp completion meeting initial Stage 3 Expansion requirements. +600m3/s and operational efficiency via allowing one-way traffic flow in twin incline upon electrification of fan chamber (mid-2026).
4
Internal Ramp System
Status: Internal Ramp Connecting the Main Mine to the Highly Productive Twin Incline
Status: Complete
Impact: Major operational efficiency improvements as the Main Mine is accessible to the highly productive twin incline and all mining fronts connected via an internal ramp, allowing for one-way traffic flow.
5
Pastefill System
Status: Commissioning of tailings filter plant started end of February 2026, practical completion of pastefill system commissioning scheduled for Q4 2026
Impact: Significant improvement to mining method plus mine flexibility via enabling mining in two directions vertically instead of currently one.
16
Near-Term Mine Transformation: Major Infrastructure Upgrades
TSX: KNT
OTCQX: KNTNF
4 metres
Existing Incline to Main Mine
Transported 1 mt (waste & ore) in 2022
6 metres
New Twin Incline (#2)
High Speed, Large Travel way, Gradual Gradient
4.5 metres
6.5 metres
Rapid Ore Transport - Twin Incline Complete
TSX: KNT
OTCQX: KNTNF
Internal Ramp System - Major Underground Milestone
TSX: KNT
OTCQX: KNTNF
First Material Pass Tonnes Moved in Early August Which Significantly Improves Material Handling Productivity
Multiple Surface Haulage Records Achieved Following Material Pass Commissioning and Integration of Surface Haulage Trucks Underground (Eliminates Need for Rehandle)
Second Material Pass Scheduled to Come Online late Q2, Enabling Dedicated Ore and Waste Passes 19
Ore Pass System - Second Material Pass Nearing Completion
TSX: KNT
OTCQX: KNTNF
15 metres
9.5 metres
The new primary fans can deliver airflow up to 3x current rates to +600m3/s (expandable to ~700m3/s via benching of the Puma Ventilation Drive). To conserve power, the fans will initially operate at ~350m3/s (+75% increase from current flow-rates) and ramp up incrementally as required.
Mechanical installation completed in late Q4, with HV electrical work and associated infrastructure now advancing.
Electrification is scheduled for completion in mid-2026 20
Fan Chamber - New Primary Fans Commissioning Planned in Mid-2026