TE
Published on 05/12/2026 at 05:17 pm EDT
May 12, 2026
Q1 2026
Earnings Call
G2_AUSTIN CONSTRUCTION: APRIL 2026
1
1
Participants and Agenda
Business updates
Concluding remarks
Key messages
▪
▪
▪
Daniel Barcelo
Chairman of the Board and Chief Executive Officer
DETAILS
ITEM
Prepared Remarks
Jaime Gualy
Chief Operating Officer
G1_Dallas update
Evan Calio
Chief Financial Officer
▪
▪
▪
Financial summary
2026 - 2027 outlook
Capital formation update
Jeff Spittel
EVP, Investor Relations and Corporate Development
Q&A
State of the Business
T1 is positioned downstream of hyperscaler demand for power and at the nexus of U.S. advanced manufacturing and policy
G2_AUSTIN CONSTRUCTION IN APRIL 2026
G2_Austin construction proceeding on schedule with foundational concrete works underway in April 2026 and erection of first steel expected in May 2026
T1 has identified and is targeting a comprehensive financing solution, which includes a significant debt component, to fund the remaining balance of capital expenditures for Phase 1 of G2_Austin in Q2 2026
T1 generated record quarterly net income from continuing operations of
$3.9 million ($0.01/share) and record quarterly Adjusted EBITDA of $9.1 MM in Q1 2026
T1 continues to qualify international cell suppliers to support the higher
end of the targeted 2026 G1_Dallas production range of 3.1 - 4.2 GW
As a major buyer of American polysilicon and a growing American advanced manufacturer building critical domestic energy supply chains, we believe that T1 is well positioned for a potential Section 232 ruling
G2_Austin: Flagship U.S. Project Update
Construction of T1's flagship U.S. solar cell
WE ARE HERE
fab proceeding on schedule
Latest from G2_Austin:
Construction proceeding
on schedule despite unusually wet weather at site in April 2026
Concrete pouring work got underway in April
KEY
DESIGN PROGRESS
Q2
Concrete work
began
Geopiers completed
90% design completed
PLE enters US Ports
Full contract award for Central Utility Plant and Water Management Plant
Issue for Construction (IFC) design completion
Steel arrives and erection of steel skeleton begins
Production Line Equipment (PLE) factory testing begins
Electrical and Mechanical contracts to be awarded
PLE enters US Ports
Q3 Q4
PLE enters US Ports
Roof and walls of main production building complete
PLE installation starts
Final commissioning And start of production
G1_Dallas Operations Update
Executing against 3GW of contracts in 2026
Production Status
Produced 683.3 MW of solar modules in Q1 2026
In April, G1_Dallas produced at a 3.4 GW annualized rate
Sales Update
T1 generated Q1 2026 total net sales of $177.6 MM vs. $53.4 MM in Q1 2025
2026 Outlook
Executing against 3 GW of firm contracts for 2026
Cell procurement for 2026 advancing to potentially support the high-end of the production guidance range of 3.1 - 4.2 GW range for 2026 with volumes weighted to H2 2026
Potential for H2 2026 pricing upside driven by AI infrastructure
6
demand and possible Section 232 ruling
G1_Dallas Q1 2026 Production and Outbound Activity Summary
T1 Financial Summary
T1 generated record quarterly Adjusted EBITDA of $9.1 MM in Q1 2026
T1 BALANCE SHEET SUMMARY
683 MW
Q1 2026 Module Production
Production expected to ramp as
2026 progresses
17%
Q1 2026 Gross Margin
Q1 performance reflects margin profile of T1's contract coverage
$9.1 MM
Q1 Adjusted EBITDA
Improvement driven by increased sales volumes under fixed margin contract and lower third-party fees
$ in millions
As of
31-Mar-26
As of
31-Dec-25
Cash, cash equivalents, and restricted cash
$124
$271
Other current assets
$469
$400
Net, property, plant, & equipment
$346
$302
Other assets
$398
$399
Total assets
$1,337
$1,372
Current liabilities
$466
$464
Other liabilities
$561
$586
Preferred stock
$73
$72
Shareholders' equity
$237
$250
Total liabilities & equity
$1,337
$1,372
Strong financial position for 2026
Q1 2026 margin improvement underpinned by fixed-margin and cost-plus offtake contracts
Adjusted EBITDA of $9.1MM benefitted from higher than forecast production and sales in Q1 and lower third-party fees
Priced upsized convertible notes offering in April 2026, generating
$175MM of net proceeds and facilitating continued progress on G2_Austin Phase 1
T1 is targeting a comprehensive financing solution, which includes a significant debt component, to fund the remaining balance of capital expenditures for Phase 1 of G2_Austin in Q2 2026
7
Several institutional investors that are among T1's top 50 holders have initiated or added to positions in T1's equity as of latest available SEC filings
2026 - 2027 Outlook
T1 is well positioned to navigate bridge year to planned G2_Austin start of production and expected step change in earnings power in 2027
INTEGRATED G1/G2 OPERATING AND FINANCIAL GUIDANCE
Production Guidance
Maintaining 2026 production guidance of 3.1 - 4.2 GW
OPERATING AND FINANCIAL GUIDANCE SUMMARY
2026E
G1_DALLAS (5GW) -G2_AUSTIN (2.1GW PHASE 1) RUN RATE
INTEGRATED G1 (5GW) - G2 (5GW) RUN RATE
Annual Module Production (GW)
3.1 - 4.2
5.0
5.0
Annual G2_Austin Cell Production (GW)
--
2.1
5.0
Estimated Adj. EBITDA ($MM)
TBA
$375 - $450
$650 - $700
T1 believes it is well positioned to achieve high-end of range based on procurement outlook for international cells from suppliers who have certified as non-FEOC
Financial Guidance
No changes to integrated G1/G2
annual Adjusted EBITDA run rate guidance
T1 is on track to achieve G1_Dallas/G2_Austin Ph. 1: $375
$450 MM run rate in 2027 based on:
G1 operating at 5.0 GW capacity
Fully ramped 2.1 GW G2 first phase
G1_Dallas/G2_Austin (Ph. 1-2): $650 - $700 MM based
on:
Market Outlook
2026: waiting on Section 232 outcome and customer safe-harboring
Potential ruling in Section 232 case, third party cell availability above 4.2 GW, customer demand for merchant volumes post July safe-harboring milestone are still unknown swing factors for 2026
Intend to issue 2026 Adjusted EBITDA guidance after the expected 232 determination
Preliminary indications of incremental G1/G2 domestic content underpinned by hyperscaler growth
Indicative customer demand for potential G1/G2 offtakes cover more than 100% of anticipated production capacity for 2027 - 2028
G1 operating at 5.0 GW capacity
Fully ramped 5.0 GW G2 (Ph. 1 and 2)
T1's Unique Commitment
to U.S. Energy Dominance
T1 is building an integrated U.S.
polysilicon-based solar supply chain
Investing in American Advanced Manufacturing Supporting the nascent U.S.
polysilicon industry
Aligned with U.S. policies that promote domestic solar
G1_Dallas: T1 is operating its state-of-the-art solar module production supporting more than 1,200 jobs in Texas
G2_Austin: expect to invest more than $400
MM on 2.1 GW Phase 1 of U.S. solar cell fab
T1 plans to develop >5 GW of production capacity at G2_Austin in two phases
Expect >5 GW G2_Austin to support up to 1,800 jobs
Domestic polysilicon production is critical to strengthen both the solar and semiconductor industries
Developing U.S. semiconductor-grade polysilicon production at scale depends upon a healthy solar-grade polysilicon sector
T1 is one of the largest buyers of U.S. polysilicon through offtake commitment with Hemlock Semiconductor
Extended supply agreement to source U.S. solar wafers from Hemlock's parent company Corning Inc.
T1 is investing in critical domestic supply chains to provide America with scalable, reliable, low-cost energy while hyperscaler capex is driving significant electricity demand growth
Potential Section 232 ruling on polysilicon and derivatives imports creates upside pricing potential for T1's modules made with U.S. poly/wafers
Entered into transactions intended to maintain eligibility for Section 45X credits
Advancing plan to produce high domestic content modules that are expected to qualify customers for Section 48E bonus credits
T1's Strategic Priorities
Positioning T1 as the first vertically integrated American
silicon-based advanced solar company
1
2
3
Fund and build G2_Austin Ph. 1
T1 is targeting a comprehensive financing solution to fund the remaining balance of capital expenditures for Phase 1 of G2_Austin in Q2 2026
Begin production of high domestic content modules at G1_Dallas with U.S. polysilicon, wafers, steel frames and solar cells
Raise capital required to begin construction of G2_Austin Ph. 2
Enhance T1's
profitability
Generate efficiencies and bolster throughput at G1_Dallas to achieve sustainable profitability
Internalize workstreams that were previously outsourced to realize cost efficiencies
Optimize T1's capital stack across key metrics including leverage, cost, complexity, and ownership as the business model matures
Grow T1's supply chain, sales
and engineering teams
Take next steps to mature T1's organization and enhance critical capabilities
Build T1's dedicated sales team to accelerate commercial development and sell out G1/G2
Create a flexible supply chain to drive domestic content strategy while harvesting cost efficiencies from global vendor network
Q&A
Disclaimer
T1 Energy Inc. published this content on May 12, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on May 12, 2026 at 21:16 UTC.