TXG.TO
TSX | TXG
Q4 2024 RESULTS CONFERENCE CALL
February 20, 2025
All amounts expressed in U.S. dollars unless otherwise stated
KEY HIGHLIGHTS & OPERATIONAL PERFORMANCE
JODY KUZENKO
PRESIDENT & CEO
STRATEGIC PILLARS
Strategy continues to evolve as significant milestones are achieved
DELIVER MEDIA LUNA TO
OPTIMIZE MORELOS
GROW RESERVES &
FULL PRODUCTION &
PRODUCTION & COSTS
RESOURCES
BUILD EPO
DISCIPLINED GROWTH &
RETAIN & ATTRACT BEST
INDUSTRY LEADER IN
CAPITAL ALLOCATION
INDUSTRY TALENT
RESPONSIBLE MINING
4
KEY HIGHLIGHTS
Original production guidance achieved for sixth consecutive year
Full-year gold production of 452,523 oz was in line with upwardly revised guidance of 450,000 to 470,000 oz
All-in sustaining costs1 of $1,156 per oz gold sold were towards upper end of guided range ($1,110 to $1,160 per oz gold sold), resulting in an all-in sustaining costs margin1 of 49% for the full year
Generated record annual revenue of $1,116M and record annual adjusted EBITDA1 of $541M
Full-year net cash generated from operating activities of $450M; negative free cash flow1 of $123M (positive $326M prior to $449M invested in Media Luna)
Exited the year with $110M of cash and $332M in available liquidity1,2
filed on SEDAR+ (www.sedarplus.ca) or on the Company's website (www.torexgold.com). See also Key Financial Metrics on slide 24 for the comparable IFRS measure.
5
2) Available liquidity includes $110 million of cash and $221 million available on credit facilities ($65 million of borrowings and $14 million utilized for letters of credit). Numbers may not sum properly due to rounding.
OPERATIONAL PERFORMANCE
Another year of solid operational results from ELG Complex in 2024
Q4 output reflects lower plant throughput in December Q4 throughput reflects temporary suspension
Quarterly grades processed stable throughout 2024
ELG Underground operating well above 2,000 tpd
6
CONSISTENT AND RELIABLE PRODUCER
2025 guidance reflects four-week tie-in period and subsequent ramp-up of Media Luna
In millions of U.S. dollars, unless otherwise noted
2024
2024
2025
Guidance3,4
Peformance
Guidance5
Production
Gold
oz
450,000 to 470,000
452,523
Not Provided
Gold Equivalent1
oz AuEq
460,000 to 480,000
461,420
400,000 to 450,000
Total Cash Costs2
By-Product basis
$/oz
860 to 910
940
Not Provided
Gold Equivalent basis1
$/oz AuEq
900 to 950
972
Not Provided
All-in Sustaining Costs2
By-Product basis
$/oz
1,100 to 1,160
1,156
Not Provided
Gold Equivalent basis1
$/oz AuEq
1,130 to 1,190
1,183
1,400 to 1,600
Sustaining Capital Expenditures2
Sustaining
$
50 to 60
61.2
85 to 95
Capitalized Stripping
$
5
1.4
---
Total Sustaining
$
55 to 65
62.6
85 to 95
Non-Sustaining Capital Expenditures2
Media Luna Project
$
430 to 450
449.0
Not Provided
Media Luna Cluster Drilling/Other
$
10 to 15
10.6
Not Provided
Total Non-Sustaining
$
440 to 465
459.6
90 to 100
1) Guided AuEq production for 2024 includes Au and AuEq values for silver (Ag) and copper (Cu) sold assuming metal prices of $1,900/oz Au, $23/oz Ag, and $3.75/lb Cu. For the year ended December 31, 2024, refer to "Gold Equivalent Reporting" in the Company's
latest MD&A for the relevant average market prices by commodity. Guided AuEq production for 2025 includes Au and AuEq values for Ag and Cu sold assuming metal prices of $2,500/oz Au, $28/oz Ag, and $4.30/lb Cu.
2) These measures are non-GAAP financial measures. Refer to "Non-GAAP Financial Performance Measures" in the Company's latest MD&A for further information and a detailed reconciliation to the comparable IFRS measures.
3) 2024 guidance assumes a MXN:USD of 18.0.
4) 2024 guidance was revised to reflect higher guided non-sustaining capital expenditure for the Media Luna Project, as disclosed in the Company's MD&A dated August 6, 2024 and higher production, as disclosed in the Company's MD&A dated November 5, 2024.
7
5) 2025 guidance assumes a MXN:USD of 20.0.
MEDIA LUNA PROJECT UPDATE
JODY KUZENKO
PRESIDENT & CEO
MEDIA LUNA PROGRESS UPDATE
Entering the home stretch with tie-in period on track for February
Engineering complete; procurement essentially complete
All major deliveries to support the start-up of Media Luna operations are now on site
Significant progress made on underground development; expect to achieve designed mining rate of 7,500 tpd six months ahead of schedule
Most definition drilling for 2025 mine plan now complete; drilling for 2026 now underway
Targeting one year of stope inventory on hand going forward
Underground development rates ahead of plan
Paste plant on schedule for commissioning in early Q2
Over 80% of total planned workforce now in place
Project Progress
Completion
Project To Date
Q4 2024
Procurement
99%
Engineering
100%
Underground development/construction
90%
Surface construction
85%
Total Project
94%
Ramp-up Timeline
Deliverable
2025
2026
2027
Q1
Q2
Q3
Q4
H1
H2
H1
H2
Media Luna Underground
(Mining Rate)
Guajes Tunnel Conveyor
5,000 tpd
6,000 tpd
6,500 tpd
7,500 tpd
Process/Flotation Plant
Paste Plant
Commercial Production
Guajes Tailings Facility
First Cu Concentrate
Construction
Commissioning
/ Ramp
-up
Steady-state
9
MEDIA LUNA PROGRESS UPDATE
First concentrate on track by end of March; commercial production shortly thereafter
Flotation plant nearing completion
Cu concentrate storage on plan
230 kV switchyard nearing completion
Paste plant construction on plan
10
Disclaimer
Torex Gold Resources Inc. published this content on February 24, 2025, and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on February 24, 2025 at 11:28:00.771.